The Ram Mandir in Ayodhya - Tracking the Temple's Construction Timeline

 The Ram Mandir in Ayodhya - Tracking the Temple's Construction Timeline

Here is a detailed look at the key milestones and progress of the Ram Mandir construction in Ayodhya, from the Bhoomi Pujan in 2020 to the expected completion by 2024.

Ram Mandir Ayodhya timeline
Ram Mandir Ayodhya timeline 

Ram Mandir Ayodhya timeline :  The Ram Janmabhoomi temple in Ayodhya, Uttar Pradesh has been one of the most controversial religious sites in India. After decades of legal battles and communal tensions surrounding the disputed land, the Supreme Court delivered a landmark verdict in November 2019 paving the way for the construction of a Ram Temple.

On August 5, 2020, Prime Minister Narendra Modi performed the Bhoomi Pujan ceremony, signaling the formal start of the Ram Mandir construction. Since then, the temple construction has been progressing at a rapid pace under the supervision of the Ram Janmabhoomi Teerth Kshetra Trust.

Overview of Ram Mandir and Its Significance 

  1. The Ram Janmabhoomi temple is being built at the place which is believed to be the birthplace of Lord Ram. 
  2. Ayodhya is regarded as one of the seven sacred cities for Hindus and attracts millions of devotees each year.
  3. The construction of a grand temple in Ayodhya has been a long-standing demand of various Hindu groups and organizations. 
  4. The Ram Mandir symbolizes the cultural and religious heritage of India. Its construction is expected to conclude one of the most polarizing issues in Indian politics.

Tracking the Ram Mandir Construction Timeline

Tracking ayodhya Ram Mandir timeline


The Ram Mandir is estimated to be built at an overall cost of ₹1,100 crores on a total plot area of 67 acres. The main temple itself will be spread over 2.7 acres. Here is an overview of some of the key milestones in the temple construction so far:

August 2020 - Bhoomi Pujan Ceremony

  • Prime Minister Modi performed the ground-breaking ceremony for the Ram Mandir amid Vedic rituals on August 5, 2020. 
  •  This ceremony marked the official commencement of the temple's construction.
  • PM Modi along with UP CM Yogi Adityanath, RSS Chief Mohan Bhagwat and other dignitaries were present on the occasion.

 September 2020 - Pillar Construction Begins 

  • By early September 2020, the digging work for temple foundations was completed.
  • Pillars that will support the foundation of the temple began to be constructed. 
  • The carved pink sandstone pillars were sourced from Mirzapur in Uttar Pradesh.

 December 2020 - Foundation Completed

  • By mid-December 2020, the construction of all 1,232 pillars that will form the temple's foundation was completed.
  •  The pillars were reinforced with concrete and red mirzapur stone covering.
  • The plinth of the temple was also completed.

 August 2021 - Main Temple Construction Starts 

  • On August 29, 2021, the construction of the main temple building commenced.
  •  This marked the beginning of the ground floor construction for the temple's sanctum sanctorum (garbhagriha). 
Ayodhya Ram mandir timeline


 December 2021 - Ground Floor Complete

  • By December 2021, the walls and plinth on the temple's ground floor was completed entirely from carved sandstone. 
  •  Intricately carved sandstone blocks from Bansi Paharpur in Rajasthan were used for construction.
  •  The ground floor sanctum sanctorum will house the idols of Ram Lalla (infant Ram).

 August 2022 – First Floor Construction Begins

  •  The construction of the first floor of the sanctum sanctorum began in August 2022.
  •  This chamber on the first floor will house the idols of Lord Ram, Lakshman and Sita. 
  • The walls and pillars on the first floor will be completed by December 2022.

 December 2023 - Completion of Main Temple Structure 

  • The entire main temple structure is scheduled to be completed by December 2023. 
  •  After this, finishing touches will be done and ornamental work will be undertaken in 2024.
  •  Intricately carved doors and windows will be installed along with decoration of the sanctum sanctorum.
Timeline ayodhya Ram mandir


 Mid 2024 - Installation of Idols and Opening

  •  The idols of Lord Ram are expected to be installed in the sanctum sanctorum by mid 2024.
  •  The final rituals, prayers and ceremonies will be conducted for the temple opening.
  •  The Ram Mandir is expected to open its doors for devotees' darshan by late 2024.

 Auxiliary Structures in Ram Mandir Complex 


Apart from the main temple, several other facilities are being constructed within the 67-acre Ram Janmabhoomi campus:

  1. Yatri Sthal - Accommodation for devotees and pilgrims.  
  2. Museum - Documenting facts related to temple and Ayodhya's heritage.
  3. Archival Center - Housing ancient manuscripts and heritage documents. 
  4. Auditorium & Prayer Hall - For religious congregations and events.
  5.  Priest Living Quarters - Accommodation for priests and staff.
  6. Front Plaza - Large gathering place for devotees.
  7. Administration Office - Managing campus affairs.
Ayodhya Ram mandir complex


The entire Ram Mandir project along with the auxiliary structures is targeted to be fully completed by 2025 end.

 FAQs


  1.  When did the construction of Ram Mandir formally begin?


  • The construction began on August 5, 2020 after Prime Minister Narendra Modi performed the Bhoomi Pujan ceremony in Ayodhya. This marked the official commencement of the temple building.

2.How much will the Ram Mandir cost to build? 

  • The total estimated cost for constructing the temple complex is ₹1,100 crores. This includes the main temple as well auxiliary structures.

3.When will the construction be completed?

  • The Ram Janmabhoomi Teerth Kshetra Trust has set a deadline of December 2023 for completing the main temple structure. The entire complex is scheduled to be ready by end of 2025.

4. How is the construction being funded?

  • The temple construction is being funded by donations from millions of Hindus across India and the world. The Shri Ram Janmabhoomi Teerth Kshetra trust has been set up to oversee fund collection and temple planning.

 5.How many floors will the temple have? 

  • The Ram Mandir will have three floors - ground, first and second floor. The sanctum sanctorum will be on the ground and first floors while the second floor will have ancillary space.

6. Will the public be allowed inside the new temple?

  • Yes, once the construction is complete, the Ram Mandir is expected to be opened for devotees' darshan by mid to late 2024 after the idols are installed.

 Conclusion

The construction of a grand Ram Temple in Ayodhya has been a long-cherished dream for millions of Hindus globally. With the Supreme Court verdict clearing the way in 2019, the temple construction has been proceeding smoothly since the Bhoomi Pujan in 2020. 

The Ram Janmabhoomi Teerth Kshetra Trust has set an ambitious timeline to complete construction by end 2024. Given the rapid progress so far, it appears the Ram Mandir will meet its deadline if things continue as planned. This will mark the culmination of one of the most protracted ideological battles in India. 

From the foundation laying to the sanctum sanctorum completion, each milestone in the temple construction has been commemorated with great fervor. The opening of the Ram Mandir complex promises to be a momentous occasion in the cultural history of India.